Underreamer

فهرست مطالب

HPOGC Hydraulic PDC Underreamer: A Reliable Solution for Hole Enlargement

The HPOGC Hydraulic PDC Underreamer is a hard-wearing downhole tool designed to enlarge the borehole diameter beyond the bit size in a controlled and efficient way. Installed as part of the bottom-hole assembly (BHA), it uses hydraulic energy from drilling fluid to open and close its cutting arms downhole. This capability makes it a powerful solution for section enlarging jobs where precise hole size and dependable performance are critical.

The underreamer features robust PDC cutting elements mounted on arms that can be repeatedly opened and closed. The tool’s simple and efficient arm design increases longevity, improves reliability, and facilitates field maintenance. Optimized mud port placement ensures thorough cleaning of the PDC cutters, supports higher reaming rates, and reduces the risk of pack-off during hole enlargement operations.

Design and Working Principle

The underreamer is built around a hydraulic piston system that actuates three cutting arms. When drilling fluid is circulated through the tool, hydraulic pressure acts on the piston and forces the arms outward into the underreaming position. Reducing or stopping flow allows the arms to retract back into the body for safe passage through casing and restrictions.

Key design elements include:

  • Three-arm configuration for balanced cutting and stable operation.

  • Integral stabilizer blades on the body to improve BHA stability and control.

  • Minimal moving parts (essentially a piston and three arms), which reduces mechanical complexity and enhances reliability.

  • Optimized mud port layout that directs flow across the PDC cutters for cooling and cleaning while maintaining the pressure differential needed to operate the piston.

  • Versatile body/arm configuration, allowing each body to be fitted with various cutter arm sizes within its operating range.

This combination of hydraulic actuation, simple mechanics, and strategic fluid management enables repeatable, controlled hole enlargement in demanding drilling environments.

Key Applications in Drilling and Well Completion

The HPOGC Hydraulic PDC Underreamer is suitable for a wide range of drilling, work-over, and completion operations, including:

  • Remedial underreaming for running expandable casing/liners
    Creating the necessary clearance to successfully run and expand casing or liner systems.

  • Section enlargement where diameter restrictions exist
    Enlarging specific intervals where previous operations or constraints limit the available diameter.

  • Gravel packing during work-over operations
    Preparing the wellbore with sufficient annular space for gravel packing assemblies.

  • Wiping out bridges and key seats
    Removing mechanical bridges and key seats that restrict tool movement or casing running.

  • Providing adequate annular space for cementing
    Ensuring sufficient clearance between casing and formation for effective cement placement.

  • Gravel packing in gas storage wells
    Enlarging selected sections of gas storage wells to improve gravel pack design and placement.

  • Section enlarging and window opening jobs
    Supporting operations where a window is cut in casing and the open-hole section below needs enlargement.

  • Increasing inflow diameter in the pay zone
    Expanding the wellbore diameter in the production interval to enhance inflow potential.

  • Removing mud invaded zone in reservoir sections
    Underreaming to remove mud-damaged zones and expose cleaner formation for better productivity.

These applications make the tool a versatile choice for operators seeking to improve well construction quality and production performance.

Models and Technical Specifications

The underreamer is available in several body sizes, each compatible with a defined range of cutter arm sizes and connection types.

Body and Cutter Arm Range



TypeBody ODHard Facing ODStandard Cutter Arms (hole size)Top ConnectionBottom ConnectionNo. of Arms
UR 5505 1/2″6″7″ to 14″3 1/2 IF3 1/2 IF3
UR 5755 3/4″6″7″ to 14″3 1/2 IF3 1/2 IF3
UR 8008″8 1/2″9 1/4″ to 18″4 1/2 IF4 1/2 IF3
UR 120012″12 1/4″13 1/2″ to 16″6 5/8 REG6 5/8 REG3
UR 175017 1/2″17 1/2″19″ to 26″7 5/8 REG7 5/8 REG3

One common configuration, for example, is a 12 1/4″ cutter arm on the UR 800 body, fitted with two rows of premium PDC cutters for high-efficiency hole enlargement in medium to large hole sizes.

Hydraulic and Mechanical Limits


FactorUR 575UR 800UR 1200UR 1750
Max Flow (USG/min)3505008001200
Max Weight on Bit (metric ton)581520
Max Weight on Bit (klbs)1117.63344
Max Torque (daN·m)45070012001600
Max Torque (lbs·ft)33005200880011800
Rotation (RPM)80–12080–12080–12080–120
Make-up Torque (daN·m)2000–24003200–36005500–60008000–8600
Make-up Torque (klb·ft)14.1–17.623.6–26.540.6–26.559.0–63.4
Fishing Neck Diameter5 1/4″6 1/4″8 1/2″12″




These values provide the operating envelope for typical applications and should be respected to ensure safe and efficient use of the tool.

Maintenance Plan and Recommended Tools

The underreamer is designed for field-serviceable maintenance. A typical maintenance setup includes:

  • Large floor-mounted packer vise

  • Punch set and centre punch

  • 24-in. and 36-in. pipe wrenches

  • 36-in. strap wrench

  • Medium-size shop hammer

  • Large and small flat-blade screwdrivers

  • Wire brush and flat file

  • Adjustable shop stand

  • Allen wrench set

  • Snap-ring pliers

  • Clear grease containing no solids

  • API-type thread lubricant

  • Brass or aluminum bar for controlled hammering

  • Thread taps (e.g. 3/8-16, 1/4-20, 3/8-24)

Having these tools available allows technicians to perform routine servicing, component replacement, and detailed inspection in the field or workshop.

Thread Lubrication and General Assembly Practices

Proper lubrication and handling of threaded and sealing components are essential for reliable operation:

  • Use JET MARINE 2571 Modified grease on all straight threads.

  • Use API-modified thread dope on all premium thread connections, unless otherwise specified.

  • Do not use thread dope on elastomeric seals; instead, use a silicone-based grease on all O-ring and T-seal elastomers during assembly.

  • Do not force threads that feel as though they are galling; break the connection at the first sign of galling and inspect threads for damage.

  • Ensure all components are properly aligned during make-up; apply controlled taps as required rather than excessive wrench force.

  • Avoid clamping or wrenching directly on thin-walled components that may deform or be damaged.

  • Support long assemblies correctly in the vise using adjustable stands so that they remain level.

  • Support the ends of assemblies during make-up and break-out to prevent undue stress on thread connections.

  • Verify that all parts, drill holes, and seal bores are clean and free from cuttings or foreign bodies.

  • Carefully inspect sealing surfaces before assembly for any defects.

  • Thread protectors should remain installed until the component is ready to be assembled and re-installed immediately if parts are removed from the vise.

  • Set screws must be installed and tightened evenly to avoid distortion, especially on slender or thin components; do not over-tighten.

These practices help to protect critical sealing and threaded surfaces, extend service life, and reduce the risk of downhole failures.

Assembly Overview

The full assembly procedure is detailed and stepwise. The main stages can be summarized as follows:

  1. Prepare the work area
    Clean the work area and remove any components not associated with the assembly. Gather all parts on a pallet or cart and verify them against the bill of materials to ensure nothing is missing or extra.

  2. Identify special tools and consumables
    Confirm that all required special tools, fixtures, lubricants, seals, and control-line connectors are available.

  3. Assemble the piston and nozzles

    • Install the nozzle O-ring into the carry nozzle and screw the nozzle into place.

    • Install both O-rings on the carry nozzle.

    • Make up the carry nozzle sub-assembly on the piston.

    • Install the nozzle and nozzle O-ring in the rod piston as required.

  4. Install guiding elements and seals

    • Install guide rings and spring on the rod piston.

    • Make up the piston on the rod piston to achieve the specified distance between piston and rod piston faces.

    • Install the piston O-ring.

  5. Install indicating sleeve and subs

    • Install the two O-rings in the indicating sleeve and insert the sleeve into the body.

    • Screw the bottom sub onto the body.

  6. Insert piston sub-assembly into the body
    Insert the piston sub-assembly into the body; this makes subsequent piston positioning easier.

  7. Use the adjusting tool

    • Install the adjusting tool on the body.

    • Turn the handle to push the piston forward until it stops against the body.

  8. Install arms and axle

    • Fully screw in the set screw.

    • Position the arms in the body windows and install the axle through the housing.

    • Tighten all related screws carefully.

  9. Set arm clearance and adjust opening

    • Back off the set screw until it just contacts again, repeating as necessary to achieve correct clearance.

    • The goal is to ensure that, in the closed position, the arm does not bear against the upper stem and is not under stress.

    • Check clearance by hand. If further adjustment is required, insert the rotating stem into the piston, adjust piston position to remove contact between rod piston and arm, and repeat until a slight clearance is obtained.

  10. Complete assembly

    • Remove the rotating stem and adjusting tool.

    • Install the top sub on the body.

    • Compare the finished assembly with the assembly drawing and confirm that all components are correctly installed and no piece from the bill of materials is left unused.

Disassembly Overview

Disassembly follows a controlled reverse sequence:

  1. Clean the work area and remove any unrelated components.

  2. Unscrew the top sub and bottom sub from the body.

  3. Install the adjusting tool on the body and turn the handle to push the piston until it stops against the body.

  4. Fully screw the set screw and remove the axle from the housing.

  5. Remove the arms from the body and repeat the piston/tool steps as required for all arms.

  6. Remove the adjusting tool from the body.

  7. Push on the end of the rod piston with a bar to remove the piston sub-assembly from the body.

  8. Remove the indicating sleeve from the body.

  9. Unscrew the piston and remove the spring and guiding ring.

  10. Unscrew the carry nozzle and nozzle from the piston and remove the nozzle O-rings and carry nozzle O-rings.

  11. Remove the piston O-ring.

  12. Clean and thoroughly inspect all parts for wear or damage before re-use or replacement.

Operational Procedure for Hole Enlargement

1. Shallow Test

Before running the underreamer to bottom, a shallow test is recommended:

  • Connect the tool to the pilot assembly and apply the recommended torque on the bottom connection.

  • Measure and record the distance from the end of the BHA to the arms.

  • Make up the top connection and complete the BHA.

  • Connect the BHA to the top drive or Kelly and lower the tool below the rig floor so that the arms are fully visible while avoiding mud splash.

  • Start pumps at minimum flow and gradually increase flow until the arms fully open. Record the flow rate required to fully open the arms and, if needed, the pressure drop.

  • Stop circulation, bring the tool back to surface, and verify that the arms have correctly closed. The tool is then ready to be run in hole.

2. Underreaming Operation

During the underreaming operation, the following points are critical:

  • PDC inserts are not suitable for casing milling. Begin underreaming a few meters below the casing shoe and never circulate while moving the tool inside casing.

  • Before opening the arms, record the neutral up/down weight and torque.

  • Start circulation, start rotation, and allow a few minutes without moving the tool axially so that the arms begin cutting into the formation. Depending on arm size and section diameter, monitor torque before starting to move down.

  • Begin moving down slowly with minimum weight on bit (WOB) while watching torque and ensuring that the arms open fully.

  • Never apply full weight when the arms are only partially open, as this may seriously damage the arms.

  • Once the arms are fully open—confirmed by comparing torque with arms closed and open, preferably in a previously underreamed interval—additional weight and higher RPM can be applied within the recommended limits.

  • The underreamer can be opened and closed multiple times downhole if required.

  • At the end of the job, stop circulation to close the arms and avoid moving up with arms open.

  • When re-entering casing, proceed slowly and watch for any overpull that might indicate arms not fully closed or mechanical interference.

  • Once at surface, wash the tool thoroughly with water or appropriate fluid.

3. Pumping Through Fixed Nozzle

The tool can also be configured for pumping through a fixed nozzle. Nozzle and carry nozzle design ensure proper flow distribution, pressure drop for actuation, and effective cooling/cleaning of the PDC cutters while underreaming.

HSE Guidelines for Safe Operation

Safe handling, assembly, and testing of the underreamer require strict adherence to HSE practices:

  • Maintain good housekeeping in the work area.

  • Always use appropriate personal protective equipment (PPE):

    • Safety glasses

    • Gloves

    • Steel-toed safety shoes

    • Hard hat where required

  • Ensure all hand tools are in good condition; hammer and punch heads should not be mushroomed, and wrenches must have sound jaws and straight handles.

  • Keep tools free of oil and grease to prevent slipping.

  • Tie back or cover long hair to avoid entanglement.

  • Do not wear jewelry such as necklaces, bracelets, rings, or watches.

  • Avoid loose or torn clothing, and do not wear items like ties, scarves, or ribbons that could get caught in machinery.

  • Do not manually lift heavy loads beyond safe limits; use suitable lifting equipment (slings, forklifts, cranes, etc.) and proper lifting techniques. Only trained and qualified personnel should operate lifting devices.

  • Inspect slings, chains, cranes, forklifts, and other lifting equipment before use.

  • Many fixtures and test accessories are heavy and awkward; use correct lifting and handling procedures and keep fingers away from pinch points.

  • When lifting assemblies, ensure slings or forks are placed wide apart to keep the load stable and avoid tilting or dropping.

  • Slings and forks must not contact slips, exposed sealing surfaces, sealing areas, or components that are shear-pinned.

  • Protect exposed collets and springs and never place hooks in threaded ends.

  • During handling and assembly, keep hands and fingers away from thread connections and between moving parts; use special handling tools when necessary.

  • Some components, such as slip teeth and threads, are sharp enough to cut skin; never run bare fingers across threads or sharp edges—wear gloves instead.

  • Be aware of chemicals used for cleaning equipment; identify any hazardous substances and take precautions to prevent inhalation or skin absorption.

  • Pressure testing creates the risk of projectiles if any equipment fails. Maintain all test equipment in good order, identify weak links, and remove as much air as possible from the system. Use dedicated test bays when available.

  • If no dedicated test area exists, evacuate the area during pressure tests and restrict access to essential personnel only.

Conclusion

The HPOGC Hydraulic PDC Underreamer is a robust, field-proven solution for controlled hole enlargement in oil and gas wells. Its simple hydraulic design, minimal moving parts, integral stabilization, and flexible body/arm configurations offer a reliable platform for applications ranging from remedial underreaming and gravel packing to pay zone enlargement and removal of mud-invaded zones.

Clear technical specifications, a well-defined maintenance plan, detailed assembly and disassembly guidelines, and comprehensive operational and HSE procedures together provide a solid framework for safe and efficient use of the tool in demanding drilling environments. This combination of performance, serviceability, and safety makes the HPOGC Hydraulic PDC Underreamer a strong candidate for any project requiring high-quality hole enlargement.

Iran’s upstream oil and gas market includes more than state-owned field operators. Private companies, publicly listed contractors, holding-affiliated businesses and specialized oilfield service providers participate in exploration and production, drilling, well construction, directional drilling, MWD/LWD, completion and equipment supply.
This guide maps Iran’s upstream oil and gas sector through NIOC and its major production, drilling and development companies. It explains the roles of NISOC, POGC, IOOC, AOGPC, KEPCO, NIDC and PEDEC and shows how these organizations fit within the upstream industry.

فهرست مطالب