Hamrah Pooshesh Company Projects: From Past to Present
Whip stock 45 sets
Employer
National Iranian South Oilfields Company
Contract number
53-74-2321
Contract date
1402
Work progress percentage
90%
Multi-stage ESS - First-time production
Employer
National Iranian South Oilfields Company
Contract number
53-74-2377
Contract date
1403
Work progress percentage
20%
Grinder and recycling tool suitable for pellets with CRA material - first production
Employer
National Iranian South Oilfields Company
Contract number
53-74-1125
Contract date
1403
Work progress percentage
30%
42 Whipstock and 33 MILL
Employer
Falatghareh
Contract number
Tender:
90/1401/1اف/ت
Contract date
1403
Work progress percentage
15%
Construction types MILL
Employer
Mapna Noor Kish
Contract number
1400000270
Contract date
1403
Work progress percentage
60%
TAPER MILL 12"
Employer
Ekteshaf
Contract number
WORK ORDER: 7000230
Contract date
1403
Work progress percentage
30%
"WHIPSTOCK 9 5/8"
Employer
Petro Iranian Karkhe
Contract number
1403-10250
Contract date
1403
Work progress percentage
0%
DIRECTIONAL DRILLING SERVICES
Employer
Oil, gas and energy Keyson
Contract number
KOG-AVD-S-03-023
Contract date
1404
Work progress percentage
0%
Construction "ESS 7
Employer
North Drilling Company
Contract number
60258
Contract date
1404
Work progress percentage
0%
Construction and drift WHIPSTOCK + MILL + BRIDGE PLUG
Employer
Karian Kish
Contract number
BP-004
Contract date
1404
Work progress percentage
0%
Registered Achievements of Hamrah Pooshesh Company
Design and installation of a 7-inch bridge plug in Phase 11 of the South Pars Gas Field, Rig MD1, using the coil tubing system of the Pars Oil and Gas Company (POGC)
First-time fabrication contract for the Multi-Zone Sand Control System, awarded by the National Iranian South Oil Company (NISOC)
First-time fabrication contract for millers and retrieval tools for CRA (Corrosion Resistant Alloy) packers, commissioned by NISOC
Exclusive sales and service contract as the primary contractor for all operational fields under the National Iranian South Oil Company (NISOC) and the exclusive supplier to the Iranian Offshore Oil Company (IOOC)
Completion of drilling and deployment of a 12 1/4-inch bit, achieving a record penetration rate of 4.2 meters per hour, on Rig Fath 72, Well 533, Ahvaz, for NISOC
Successful installation and deployment of a 13 3/8-inch whipstock for the first time on North Drilling Company Rig No. 117, Ramhshir-15 Well, under Exploration Management Company
Design and installation of a single-stage sand control system on Rig Fath 64, Well 97, Mansouri Field, with dogleg severity of 14° and well inclination of 65°, performed for the first time in Iran, commissioned by NISOC
Design and installation of a 7-inch whipstock on Rig MD1, Well A18-08, with a well inclination of 89°, for the Iranian Offshore Oil Company (IOOC)